Timeline Percentage of Completion

product-roadmap

(Jorge Herrera) #1

Hi. When I create in Timeline a series of activities, and some of them are completed, some partially completed, I will need to have a Percentage of Completion (POC). Ideally comparing a baseline with reality, is this possible to do in Ruum?

Thanks a lot.


(Vidya from Ruum) #2

Hi Jorge,

Thanks for using the community.

You can generate reports for your project (ruum). Please go to Lobby and click on the 3 dots on the right handside, like shown below.
.39

Generated Report will give you an high level overview of the project. - Like 50% tasks completed, 33% tasks completed.
Also, reporting version 2 is on our product roadmap.

Regards,
Vidya