Timeline does not appear when there are many tasks in a canvas


(Phoebe Poon) #1

We recently added a lot more tasks to the canvas and grouped them by sub tasks, and now the timeline just doesn’t show anymore. Numbers below show the sub tasks count that we have: 13, 7 , 3, 8 ,1 7


(Josefine) #2

Hi Phoebe,

can you give us the url of the project you are experiencing this issue?

Best,
Josefine from the Ruum team


(Vidya from Ruum) #3

Hi Phoebe,

As per our discussion via email, I am closing the issue.
Please feel free to reopen it if you face the issue again.

Thanks a lot for using the community and helping us to build a better product.

Regards,
Vidya


(Vidya from Ruum) #4

(Vidya from Ruum) #5